How long does a kitchen remodel take?
Natalie’s answer
“A full kitchen remodel typically takes 6 to 12 weeks of active construction, but the full project timeline, including design, permitting, and material lead times, is usually 4 to 6 months from contract signing to completion.”
The full kitchen remodel timeline
Most homeowners focus on the construction phase, but the full project timeline starts much earlier. At MOSS, here's what a typical kitchen remodel timeline looks like:
Design phase (4 to 8 weeks): After signing your contract, our design team meets with you to finalize the layout, select materials, and lock in cabinet specifications. Custom cabinetry has lead times of 8 to 14 weeks, so this phase runs concurrently with the permitting process.
Permitting (2 to 6 weeks): Most kitchen remodels in Northern Virginia, Maryland, and DC require permits, especially if you're moving plumbing, electrical, or walls. Permit timelines vary by jurisdiction; Arlington and Fairfax typically take 2 to 4 weeks; DC can take 4 to 8 weeks for full reviews.
Construction (6 to 12 weeks): Active construction begins once permits are approved and materials are on-site. Demolition is fast (1 to 2 days), but rough-in work, cabinet installation, countertop templating (after cabinets are set), and finish work take 6 to 12 weeks depending on scope.
What slows projects down?
The most common delays are permitting surprises, material back-orders (especially appliances), and change orders discovered mid-project (e.g., hidden water damage or outdated electrical panels). MOSS's pre-construction discovery process is designed to surface these issues before work begins.